Initial Environmental Examination of Construction of LPG Bottling, Filling and Storage Plant Project

Narrative Description of Project: The objective of this project is to construct an LPG Bottling, Filling and Storage plant of 100 metric tons capacity. LPG Bottling, Filling and Storage Plant will be built on 20 Kanal of land. The project is to construct a new LPG Bottling, Filling and Storage Plant with initial capability around 100 metric tons capacity. The estimated cost of LPG Bottling, Filling and Storage Plant is Rs. 100 million which will be required to set up and operate the project.

Name of Client: Lajpal Traders (Pvt.) Ltd

Location Within Country Mandra, Tehsil Gujjar Khan, District Rawalpindi

Year: 2018

Name of Senior Staff (Project Director/Coordinator, Team Leader) Involved :

  • Engr. Saadat Ali, Environmental Engineer/Team Leader
  • Mr. Ali Abdullah, Enviro-civil Engineer
  • Mr. Wajahat Saeed, Environmental Engineer
  • Engr. Tehreem Fatima, Enviromental Engineer
  • Engr. Iram Sifat, Environmental Engineer

Description of Actual Services Provided by Staff:

The services included:

  • Collected Baseline (Physical, Biological and Socio-economic) of the project area
  • Identified and assessed of all major and minor impacts during Pre- construction, Construction and Operation phases of the Project;
  • Identified all significant impacts that may require detailed assessment;
  • Proposed mitigation measures to minimize, eliminate or to compensate the potential adverse impacts identified.
  • Prepared Environmental Mitigation and Monitoring Plan
  • Prepared Plantation Plan.
  • Prepared Initial Environmental Examination Report of the project