Narrative Description of Project:
The objective of the National Radiological Emergency Coordination Centre (NRECC) Building Project is to provide a dedicated office space to Pakistan Nuclear Regulatory Authority for the Centre
Name of Senior Staff (Project Director/Coordinator, Team Leader) Involved :
- Engr. Saadat Ali, Environmental Engineer/Team Leader
- Mr. Ali Abdullah, Enviro-civil Engineer
- Mr. Adil Ashraf, Environmental Engineer
- Mr. Massab Sayed, Environmental Scientist
- Ms. Khushbakht Andleeb, Environmental Scientist
Description of Actual Services Provided by Your Staff:
The services included:
- Collected Baseline (Physical, Biological and Socio-economic) of the project area
- Identified and assessed of all major and minor impacts during Pre- construction, Construction and Operation phases of the Project;
- Identified all significant impacts that may require detailed assessment;
- Proposed mitigation measures to minimize, eliminate or to compensate the potential adverse impacts identified.
- Prepared Environmental Mitigation and Monitoring Plan
- Prepared Plantation Plan.
- Prepared Initial Environmental Examination Report of the project